PROJECT TASKS

PRE-DESIGN

SCHEMATIC DESIGN

Set Up Reference Systems

  • Set up basic system
  • Set up filing systems
  • Do Pre-Schematic Work

  • Hold SD kickoff meeting
  • Confirm client submittal requirements
  • Research code requirements
  • Research special construction requirements
  • Obtain existing drawings
  • Convert existing drawings to CAD
  • Verify accuracy of existing drawings
  • Verify adequacy of existing services
  • Do Pre-Design Studies

  • Prepare special pre-design studies
  • Evaluate Building Alternatives

  • Update building program requirements
  • Prepare schematic design evaluation criteria
  • Prepare alternative building design schemes
  • Discuss alternative design schemes with consultants
  • Select engineered systems
  • Research special building treatments [put in DD]
  • Evaluate Site Alternatives

  • Update site information
  • Establish site design criteria
  • Prepare alternative site design schemes
  • Discuss alternative design schemes with consultants
  • Evaluate Parking Alternatives

  • Gather parking design aids
  • Establish parking design criteria
  • Prepare alternative parking schemes
  • Discuss alternative design schemes with consultants
  • Do Post-Schematic Work

  • Prepare reports on alternatives
  • Prepare outline spec
  • Prepare SD cost estimates
  • Assemble SD package
  • Get SD approvals
  • Handle Project Financials

  • Prepare invoice for client
  • Receive payment from client
  • Receive invoice from consultant
  • Monitor Progress

  • Monitor progress, budget, schedule
  • DESIGN DEVELOPMENT

    CONTRACT DOCUMENTS

    BIDDING

    CONSTRUCTION

    POST-CONSTRUCTION